Goyder South Wind Farm

$13M
  • SectorRenewable Energy (Wind)
  • ClientUndisclosed
  • LocationGoyder South, South Australia
  • DEC ServicesEstimating Services

Project Description

DEC Projects provided earthworks estimating for the Goyder South Wind Farm balance-of-plant package. The scope focused on civil enablement to support turbine delivery, installation and long-term access across the site.

Key Scope (Estimated)

  • ~15 km of internal access roads
  • ~360,000 m³ cut-to-fill earthworks
  • Turbine foundation works (excavation, preparation and associated civils)