Wyndham Vale Train Stabling Yard — Delivery
$173M
Project Description
DEC Projects supported delivery for the Wyndham Vale Train Stabling Facility in Melbourne’s west. The 3 km site provides four stabling roads, each accommodating two 6-car V/Line Velocity sets, with refuelling and cleaning capability and new buildings for staff amenities, security and network systems. The works included 3,500 m of new track and installation of overhead gantries to future-proof for electrification. Construction was completed over three months with zero impact to train operations.
Key Scope
- 3 km facility with four stabling roads (2× 6-car sets per road)
- Refuelling and cleaning systems
- New amenity, security and network buildings
- 3,500 m of track construction
- Overhead gantries installed for future electrification
- Three-month construction window with no service disruption